SJLS-logo-2

SINGAPORE JOURNAL OF LEGAL STUDIES

transparent
transparent

  • Journal Result

  • Case and Legislation Notes

    The Land Code – Extension of the Life of a Caveat

    Citation: [1960] Sing JLS 123
  • Case and Legislation Notes

    Chapter VI – _x000D_ Third Charter of Justice – 1855-1867 _x000D_ Sir Richard Bolton McCausland – 1856-1866 _x000D_ Sir Peter Benson Maxwell – 1856-1867 _x000D_ Sir William Hackett – 1866-1867 _x000D_ (A Judicial History of the Straits Settlements)

    Citation: [1969] Sing JLS 125
  • Case and Legislation Notes

    Privity of Contract and the Contracts (Malay States) Ordinance, 1950: Kepong Prospecting Ltd. v Schmidt

    Citation: [1968] Sing JLS 125
  • Case and Legislation Notes

    Of Limitation and the Reforms ahead the Civil Law (Amendment) Act 1982 (No. 15 of 1982)

    Citation: [1983] Sing JLS 126
  • Case and Legislation Notes

    The Basis of Restitution

    Citation: [1960] Sing JLS 126
  • Case and Legislation Notes

    The Raffles Hotel Ltd. v. Malaysian Banking Ltd.: Litigation: Its Implications for Company Law

    Citation: [1977] Sing JLS 127
  • Case and Legislation Notes

    Entrapment and “Consent in Larceny”: Martin v Puttick

    Citation: [1968] Sing JLS 127
  • Case and Legislation Notes

    Minor’s Capacity to Sue for Breach of Promise of Marriage – What is Sauce for the Goose is not Sauce for the Gander V. Rajaswary v V. Balakrishnan

    Citation: [1961] Sing JLS 127
  • Case and Legislation Notes

    Premature Service of Payment Claims Under the Building and Construction Industry Security of Payment Act—Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd

    Citation: [2018] Sing JLS 128
    In Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd, the Singapore Court of Appeal_x000D_ considered a payment claim to have been validly served although it was served earlier than the contractually stipulated date. This was because the service of the payment claim was "effective" only from the contractually stipulated date, and the claimant had had a "good reason" to serve the payment claim early. This note critically examines the reasoning in Audi vis-à-vis the existing law, the principle of freedom of contract, and the intentions of the parties in that case. In the absence of future judicial elaboration on the "effective service" and "good reason" doctrines, there is a risk that, in future, respondents may draw on these doctrines to delay or frustrate the attempts of claimants to recover payments rightly due to them. Moreover, given that the Court had found that the doctrine of estoppel would have operated in favour of the Claimant anyway, the creation of the "effective service" and "good reason" principles was not necessary.
  • Case and Legislation Notes

    Doctor Does Not Always Know Best

    Citation: [2007] Sing JLS 128